Addition in Lagrange, Wy

April, 2019: 

    Week 1: Site preparations, prepared foundation, waited for a week of no freezing temperatures, poured concrete slab. 

    Week 2:  Framed walls, sheeted walls, put in one side of windows.

May, 2019: 

     Week 1:  Attached trusses,

Adding 2 bedrooms, and a dining room, and making bathroom larger.  Adding a sliding glass door to the backyard.